  History
 
 
 

Court of Fountains Townhomes was originally created to be a forty-four unit apartment complex. We were given pre-approval in October 2002. Final approval of the apartment community was given in December 2002.

In early 2004, the goals for the Court of Fountains project changed. We decided that we would pursue a zone change and provide affordable housing for the residents of Merced County. Due to size constraints and easements for utilities, and a proposed widening project of the state highway, we reduced the number of townhomes from thirty-six to thirty-four.

 

April 2004:

April 2005:

May 2005:

July 2005:

March 2006:

June 2006:

July 2006

August 2006:

Initial approval for zone change from (R-3) High Density Residential to (P-D) Planned Development

Submission of the Final Development Plan

Plan Check

Parcel Map / Condo Map Filed

Grading Permits Issued

Grading and Infrastructure Complete. Building Permits Issued.

Club House Framed. Curbs, gutters, and slabs poured. Framing commenced on Buildings 7 & 8.

Court of Fountains Townhomes ahead of schedule. Pre-sales start date scheduled for late October. Buildings 2, 4, and 9 framing started.

 
 
 
Add to Bookmark Phone Number: (831) 655-4100 Fax Number: (831) 333-1016
 
Home | Projects | Consultants | History | News | Progress | Contact Us | Privacy
Copyright © 2006 NorthwesternDevelopment.com
Best viewed with Mozilla / Internet Explorer 5.0 and over - under 1024x768 pixels resolution.