Court of Fountains Townhomes was originally created to be a forty-four unit apartment complex. We were given pre-approval in October 2002. Final approval of the apartment community was given in December 2002.
In early 2004, the goals for the Court of Fountains project changed. We decided that we would pursue a zone change and provide affordable housing for the residents of Merced County. Due to size constraints and easements for utilities, and a proposed widening project of the state highway, we reduced the number of townhomes from thirty-six to thirty-four.
|
| |
April 2004:
April 2005:
May 2005:
July 2005:
March 2006:
June 2006:
July 2006
August 2006: |
Initial approval for zone change from (R-3) High Density Residential to (P-D) Planned Development
Submission of the Final Development Plan
Plan Check
Parcel Map / Condo Map Filed
Grading Permits Issued
Grading and Infrastructure Complete. Building Permits Issued.
Club House Framed. Curbs, gutters, and slabs poured. Framing commenced on Buildings 7 & 8.
Court of Fountains Townhomes ahead of schedule. Pre-sales start date scheduled for late October. Buildings 2, 4, and 9 framing started. |